Kazakhstan has connected 370 of 1,600 villages planned for 2026, government data show

The rural connectivity programme had reached about 23% of its 2026 village target by early October, leaving about 1,230 villages for the rest of the year.

Written with AI tools by Corridor Signal's editorial system; the publisher is responsible for it. How this site works

A steel lattice telecom tower with panel antennas and a microwave dish, its top against a grey sky
Mobile phone tower in Aspara, Jambyl Region, Kazakhstan, 2023 Photo: Nikolai Bulykin, CC BY-SA 4.0, via Wikimedia Commons, cropped

Kazakhstan had connected 370 villages under its rural connectivity programme in 2026 by early October, against a plan of 1,600 villages for the year, and had laid 11,819 km of communication lines, according to the government's summary of a 6 October session on its digital strategy, which reported figures presented by Deputy Prime Minister Zhaslan Madiyev. On those figures the programme had reached about 23 per cent of its annual village target with less than three months of the year left.

The page of Up to 150 services via eGov GPT planned to launch in Kazakhstan by year end as published online
The document as published: Up to 150 services via eGov GPT planned to launch in Kazakhstan by year end. Prime Minister of the Republic of Kazakhstan, 6 October 2026.

Meeting the plan would require about 1,230 more villages to be connected by 31 December, more than three times the number reported for the year so far. The summary does not give a monthly breakdown, a list of villages or a total for 2025.

The figures

  • Villages connected in 2026, as reported on 6 October: 370, against a plan of 1,600 for the year, or 23.1 per cent (government summary).
  • Communication lines laid in 2026: 11,819 km (same summary).
  • Villages in Kazakhstan: about 6,179, of which 42 per cent were covered by high-speed data transmission technologies in July 2025 (government release, 4 July 2025).
  • Fibre programme target: internet access for 3,781 villages by the end of 2027, more than 160,000 km added to the network and coverage raised to 90 per cent (same release).
  • Satellite: 328 more remote settlements to be connected by the end of 2025, with investment in this area above 38.6 billion tenge and OneWeb, Starlink, Shanghai Spacecom Satellite Technology and Amazon Kuiper named as partners (same release).
  • Schools: 3,998 of 7,866 general education schools connected to fibre in 2024, or 51 per cent, up from 46 per cent (Kazakhtelecom 2024 annual report).

How the targets fit together

The 2026 comparison is direct: the plan of 1,600 villages and the 370 connected appear in the same document and refer to the same year, which is the basis of the 23 per cent figure. Lines laid are not a measure of completed connections. The summary does not say how much of the 11,819 km serves villages already connected, so the Data Desk does not divide one figure by the other.

The July 2025 figures do not reconcile on their face. Coverage of 42 per cent of about 6,179 villages implies about 2,600 villages with high-speed service; adding 3,781 would exceed the total. The release does not say how many of the 3,781 already had some form of high-speed access, or whether the 90 per cent refers to villages or to people. The Data Desk therefore treats 3,781 as the scope of the fibre programme rather than as a count of villages without service, and does not calculate cumulative progress against it, because no 2025 total appears in the documents reviewed.

The Times of Central Asia, in an article published this month that draws on an interview with Madiyev, reported that Kazakhstan aims to connect more than 90 per cent of villages by fibre within roughly a year and a half to two years, with satellite services covering the remainder. On mobile networks, the government expected in July 2025 that coverage would reach 99 per cent nationwide by 2027 (July 2025 release), and its 6 October summary plans coverage along 40,000 km of regional and national highways in 2027, with more than 500 antenna-mast structures (6 October summary).

Method

Figures are taken as published in two government releases, of 4 July 2025 and 6 October 2026, and in Kazakhtelecom's 2024 annual report, all linked above. Percentages and differences are Data Desk calculations: 370 divided by 1,600 gives 23.1 per cent, and 1,600 minus 370 gives 1,230. "This year" in the October summary is read as calendar 2026. The connection counts are the government's own and could not be checked against an independent list of villages.

Document trail

4 sources, 3 primary

  1. Up to 150 services via eGov GPT planned to launch in Kazakhstan by year end

    Prime Minister of the Republic of KazakhstanPrimary source

  2. Kazakhstan's AI Strategy: Eurasia's Emerging Digital Power

    The Times of Central AsiaSecondary source

Named in this piece

  • Kazakhstan
  • Government of Kazakhstan
  • Ministry of Artificial Intelligence and Digital Development
  • Kazakhtelecom