Kazakhstan puts Data Center Valley's first phase at 304 MW
Three data centres in the Pavlodar region are due in 2027, and the first has grown to 68 MW from the 50 MW given in August.
Written with AI tools by Corridor Signal's editorial system; the publisher is responsible for it. How this site works

Kazakhstan's government has put the first phase of Data Center Valley, its data centre campus in the Pavlodar region, at three data centres with 304 MW of capacity, the prime minister's office said on 6 November.
Prime Minister Olzhas Bektenov chaired the meeting on the project's progress. Bagdat Mussin, chairman of the management board of Kazakhtelecom, reported that work at the site of the first data centre, of 68 MW, had moved from the preparatory stage to laying foundations and erecting infrastructure facilities and an administrative building. Its commissioning is scheduled for the second quarter of 2027.
The second data centre, Firebird AI, is to have 164 MW. Pit excavation there is 70 per cent complete, and completion and launch are scheduled for the third quarter of 2027. A third data centre, of 72 MW, is due to be commissioned in the fourth quarter of 2027. The meeting also discussed the project to create a third supercomputer cluster.
The first data centre has grown from 50 MW
The figures differ from those the government gave in the summer. On 13 August the prime minister's office described the first facility as having 50 MW of capacity, with excavation for its energy centres and AI factories 90 per cent complete and operation planned for June 2027. It said then that a 215 MW substation had been acquired for the project's power supply, that the main buildings of the data centre and its energy units were to be erected by the end of December 2026, and that commissioning works were to be completed in May 2027. The 6 November account gives 68 MW for the first data centre and does not explain the change.
The 2027 figure has also risen. In the passage on Data Center Valley, the government's account of 6 October said data centres with a total capacity of 186 MW were planned for commissioning in 2027, followed by another 109 MW in the second quarter of 2028. The three Pavlodar data centres alone add up to 304 MW, all scheduled within 2027. The October account also said that land had been allocated in Ekibastuz, an operator identified and power supply from the GRES-1 power station secured, that a $10 billion package of agreements had been signed with Firebird AI, and that more than 20 international technology companies and investors had shown interest. Corridor Signal covered the October figures in its report on the 295 MW target.
Phase two rests on preliminary agreements
For the second phase, preliminary agreements have been signed with Gaw Capital, Boosteroid and Firebird to locate 480 MW of computing capacity, with the possibility of expansion to 620 MW, the government said. Negotiations are under way with Aleria, Energy Capital Global and China Energy for a further 240 MW, with prospects of increasing that to 420 MW. By 2029 the campus is planned to reach 1 GW.
Zhaslan Madiyev, deputy prime minister and minister of artificial intelligence and digital development, cited an assessment by KPMG that puts the project's potential export revenue at $3.1 billion a year and cumulative investment over the 20-year life of the data centres at $115 billion. The account gives neither the date nor the method of the assessment. Energy Minister Yerlan Akkenzhenov and the akim of the Pavlodar region, Asain Baikhanov, reported on supplying the project with power and utility infrastructure.
Bektenov instructed the Ministry of Artificial Intelligence and Digital Development and Kazakhtelecom to ensure the centres are built and launched within the established deadlines. For operators and cloud buyers in the region, those dates are now specific: three data centres due in successive quarters of 2027, and a second phase that rests on preliminary agreements rather than signed contracts. The Data Centre Pipeline tracks the project against capacity reported as commissioned.
Document trail
3 sources, 3 primary
Named in this piece
- Kazakhstan
- Data Center Valley
- Kazakhtelecom
- Firebird
- Gaw Capital
- Boosteroid
- Aleria
- Energy Capital Global
- China Energy
- KPMG
- Ministry of Artificial Intelligence and Digital Development of Kazakhstan