Turkcell activates all 54 MW of its data centres as server demand slows

Memory supply constraints delayed some customer demand, the chief executive said, while the first module of the Google Cloud build is due in 2028.

Written with AI tools by Corridor Signal's editorial system; the publisher is responsible for it. How this site works

Cover card: Türkiye, data centres, Turkcell's data centres reach 54 MW

Turkcell now runs 54 MW of active IT capacity across four data centres, but constraints on memory supply have delayed some customer demand, Ali Taha Koç, its chief executive, told analysts on 9 November.

"We now have 54 megawatts of active IT capacity across 4 locations," Koç said on the call, according to a transcript published by The Motley Fool. He said "global RAM and memory supply constraints and geopolitical uncertainties have led to some delays in customer demand", and that the company therefore expected "a more gradual revenue growth trajectory this year" in its data centre and cloud businesses.

Investment pledged for the Google Cloud region in Türkiye, and the national targetUS$ billion
Source: Investment Office of the Presidency of the Republic of Türkiye, Turkcell and Google Cloud to Establish Türkiye's First Hyperscale Regional Data Center, 25 November 2025

That means all of the four sites' potential capacity is now commissioned. At the end of 2025 Turkcell had 50 MW of IT load commissioned out of a potential 54 MW, its annual report said, and Kamil Kalyon, the chief financial officer, told analysts that the company had activated the last module of its Ankara data centre in the quarter. Further capacity will come from new buildings, the first of them for the Google region in 2028.

Customers wait for chips

The third-quarter results release says Turkcell aims to advance its data centre and cloud services, where it says it holds a leading position in Türkiye, through GPU-based cloud services and next-generation AI infrastructure. It gives no revenue figure for the business. Digital business services, the unit that sells technology projects to corporate customers, grew 65.3 per cent in the quarter, as our report on the results set out.

Asked about the slower growth, Koç said that business customers were postponing their investments and that "the demand for the servers are diminishing right now." "There is a huge RAM and memory crisis," he said, and his explanation of where supply was going was short: "Everything goes to the AI chips." He said he hoped for better growth in the data centre business later.

Some spending has also been deferred. Kalyon said part of the capital expenditure planned for data centre and renewable energy projects had shifted to later periods because of schedule changes. Operational capital expenditure, excluding licence fees, was 22.8 per cent of revenue in the first nine months, the release says, which Kalyon said was below the full-year guidance of 25 per cent.

Energy, the other large cost of running a data centre, took a smaller share of the group's revenue. Energy expenses fell to 1.8 per cent of revenue in the quarter from 2.3 per cent a year earlier, the release says, and it credits the company's solar investments, including a 16.3 MW plant in Ankara activated in the quarter. Its ground-mounted solar plants now have 175.4 MW of installed capacity, of which 90.8 MW is active.

The Google build runs to 2028

The next block of capacity is tied to Google. Under the partnership the two companies announced in November 2025, Google committed $2bn over 10 years and Turkcell planned $1bn for a Google Cloud region in Türkiye, a joint total of $3bn, the Investment Office of the Presidency said. Mehmet Fatih Kacır, the industry and technology minister, said at the time that Türkiye would mobilise $10bn of data centre and AI investment by 2030.

Construction of the Ankara facilities for the Google Cloud region was moving fast, Koç said, and the shell and core construction would be complete at the end of the year. Kalyon said the first module was scheduled for delivery in 2028 and that the company was "establishing 3 more data centers for the region." The partnership release of November 2025 described the deal as a multi-year investment and gave no capacity figure.

A candidate for a listing

Kalyon said Turkcell would most probably not need additional funding for 2026, and that it was looking at external financing for the data centre build. He went further on ownership. "I think the most important candidate for the IPO is our data center operations right now," he said, adding that the company could consider strategic partnerships or a listing for the business once the Google project was finalised.

For buyers of capacity in Türkiye, the call sets the timetable. All of the capacity in Turkcell's existing four sites is now active, and the next block it has announced comes with the Google region, whose first module is due for delivery in 2028. That is the same year Digital Realty and Rönesans Infrastructure plan to complete their Ankara campus designed for more than 22 MW.

Document trail

4 sources, 3 primary

  1. Turkcell Iletişim Hizmet: Third Quarter 2026 Results

    Turkcell via Business WirePrimary source

  2. Turkcell (TKC) Q3 2026 Earnings Call Transcript

    The Motley FoolSecondary source

  3. Turkcell and Google Cloud to Establish Türkiye's First Hyperscale Regional Data Center

    Investment Office of the Presidency of the Republic of TürkiyePrimary source