EDB signs $31.2m for Akashi, its first data centre construction project
The bank's October release puts the Astana campus at 100 MW and $354m, against 41 MW of IT capacity and $230m in its June release.
Written with AI tools by Corridor Signal's editorial system; the publisher is responsible for it. How this site works

The Eurasian Development Bank has signed $31.2 million of financing for the AKASHI data centre in Astana, the first data centre construction project in its investment portfolio, the bank said on 19 October.
The bank put the campus at a planned total capacity of 100 MW, with about 10 MW in the first phase, and total investment at about $354 million. The first phase is due to start commercial operations in 2027, and its design documentation holds the Uptime Institute's Tier IV Certification of Design Documents.
The October figures differ from the ones the same bank published in June. On 26 June the EDB said it had agreed key terms with AKASHI DATA CENTER PLC for $90 million to finance the first construction phase, of 10 MW and 520 server racks, with total planned investment of about $230 million. It described the full facility as 41 MW of total IT capacity and 3,520 racks, all to Tier IV.
The June text measures IT capacity and the October text total capacity. The October release gives no rack count and does not mention the $90 million in key terms agreed in June.
The October release describes four independent data centre modules and a separate module for high-density AI and high-performance computing with liquid cooling. The campus is to be carrier-neutral, with four independent optical fibre entry points.
Sergey Ignatov, the EDB's Senior Managing Director and Head of the Project Block, said: "AKASHI Data Center supports Kazakhstan's strategic focus on developing its digital economy and artificial intelligence."
One carrier has signed a memorandum to place equipment on the site. AKASHI Data Center PLC and TT International, the international unit of Türk Telekom, signed a memorandum under which TT International can install its own telecom equipment in a dedicated zone of the data centre, Digital Business reported on 22 September. The partners plan a low-latency route between Central Asia and Europe, from Astana to London or Frankfurt, the publication said.
The project sits beside larger state-backed plans that Corridor Signal has tracked, including the national capacity target for 2027 and 2028 and the first phase of Data Center Valley in the Pavlodar region. AKASHI's first phase of about 10 MW is small next to those plans. With TT International, the company aims to attract hyperscalers, large enterprises, banks, brokers and fintech firms, Digital Business reported.
Document trail
3 sources, 2 primary
Named in this piece
- Eurasian Development Bank
- AKASHI Data Center PLC
- TT International
- Türk Telekom
- Uptime Institute
- Sergey Ignatov
- Kazakhstan
- Astana