Deals and MarketsBrief
IT Park expects to sign its Syrdarya tech centre works contract in December
A World Bank notice puts the contract in December and the build at 426 days; the bank's last status report put construction in the second part of 2027.
Written with AI tools by Corridor Signal's editorial system; the publisher is responsible for it. How this site works

Uzbekistan's IT Park expects to sign a contract in December to build its IT-enabled services centre in Gulistan, Syrdarya region, with a construction period of 426 days, a World Bank procurement notice published on 24 November said.

The notice asks consulting firms to express interest in supervising the build, acting as the Engineer under the works contract. The building has two blocks for IT companies, start-ups, training centres and IT Park's regional office. The supervision assignment is expected to last about 27 months, including a 12-month defects liability period, and is estimated at $180,000. Only firms registered in Uzbekistan with the right to supervise construction can apply, and each needs two completed supervision contracts in seismic zones of intensity 7 or higher. Expressions of interest are due on 9 December.
The notice gives no date for the start of works. The bank's status report for the project, archived on 4 September, said design documents for new regional offices were still awaiting approval and that construction "is expected to start in second part of 2027". The notice does not say whether that timetable has changed. A March request for supervision in Bukhara and Syrdarya regions was estimated at $800,000; the new notice covers Syrdarya alone.
IT Park also published a notice on 17 November for an international adviser on AI and technology partnerships to its chief executive, for 12 months, estimated at $100,000, with applications due on 1 December. The adviser is to spend at least 5 working days a month in Tashkent.
Both assignments are paid from the Uzbekistan Digital Inclusion Project, a $50 million International Development Association credit whose largest component, $35 million, covers regional infrastructure and incentives for IT-enabled services. Corridor Signal described the project's slow progress on its regional offices in October. The sector the centres serve took 2.7 per cent of the economy in the first nine months, the statistics agency said, as reported this month.
Document trail
5 sources, 5 primary
Named in this piece
- IT Park Uzbekistan
- World Bank
- International Development Association
- Uzbekistan Digital Inclusion Project
- Uzbekistan