EBRD says Türkiye's grid could host about 23 frontier AI data centres

Nearly half the economies in the bank's study could not add one 262 MW facility without raising peak load, its new Transition Report finds.

Written with AI tools by Corridor Signal's editorial system; the publisher is responsible for it. How this site works

Cover card: EBRD regions, data centres, Power grids set the limit for AI data centres

Türkiye's power system could take roughly 23 frontier AI data centres of 262 MW each if every facility paused during the busiest 1 per cent of hours, the European Bank for Reconstruction and Development said in a report published on 17 November.

About how many frontier AI data centres each power system could host if each paused in the busiest 1 per cent of hoursfacilities of 262 MW, approximate
Source: European Bank for Reconstruction and Development, Transition Report 2026-27: Frontiers of competitiveness, page 79, 17 November 2026

Poland could take about 8 on the same basis and the United States about 265, the report says. Nearly half of the EBRD economies covered could not accommodate a single frontier AI data centre without raising peak load, the Transition Report 2026-27 says. Its text gives no such figures for Kazakhstan, Uzbekistan or the South Caucasus. The estimate sits in the chapter on building an AI economy, one of five in the report alongside chapters on comparative advantage, defence spending, entrepreneurship and structural reform. Campuses planned in the corridor are measured in the same hundreds of megawatts, among them Kazakhstan's Data Center Valley, whose first phase is put at 304 MW.

The bank made the same point in its announcement of the report. "Power constraints also limit countries' ability to host large-scale data centres," it said.

Türkiye, the Caucasus and Central Asia drew similar sums

Türkiye, eastern Europe and the Caucasus, and Central Asia each attracted between $1.2bn (€1.1bn) and $1.5bn (€1.3bn) of announced foreign data centre investment from 2019 to 2025, the report says.

Sub-Saharan Africa drew the most in the bank's regions, at $9.7bn (€8.6bn), followed by its economies inside the European Union at $7.8bn (€6.9bn).

Cross-border investment in data centres across the bank's regions has stayed at about 0.07 per cent of GDP since 2018, the report says, while the equivalent figure for the world as a whole has accelerated sharply since 2023, averaging about 0.3 per cent of GDP a year.

The bank's unit of 262 MW describes the power of an average frontier AI data centre. By comparison, Turkcell runs 54 MW of active IT capacity across its four data centres, a measure of IT load rather than total power.

Global demand on course to double by 2030

Data centres consumed an estimated 485 terawatt hours of electricity worldwide in 2025, the report says. It expects their demand to roughly double by 2030, to about 3 per cent of global electricity demand.

The United States and China are expected to account for 78 per cent of the global increase in data centre capacity from 2025 to 2030. In Europe, close to 80 per cent of data centre operators cite access to electricity as their biggest challenge, the report says.

The global stock of AI computing capacity reached the equivalent of about 20 million H100 chips at the end of 2025, the bank estimates. Of 920 notable AI models released since 2010, only two involved a developer based in the EBRD regions.

A small share of AI exports

The bank's economies supply 0.8 per cent of global AI-related exports, against about 8 per cent of global goods exports, the EBRD said. In Central Asia and in eastern Europe and the Caucasus, as in the southern and eastern Mediterranean and sub-Saharan Africa, only 2 per cent of products close to AI are exported competitively, against a global average of 5.7 per cent.

AI could add up to 0.7 percentage points a year to labour productivity growth in the bank's economies over the next decade under a moderate adoption scenario, the EBRD said. The report finds the gains much smaller in lower-income economies in Central Asia, the southern and eastern Mediterranean and sub-Saharan Africa.

Kazakhstan was among the first economies in the bank's regions to require that some data be stored at home. Latvia introduced the first such requirement in 1992, followed by Estonia, Kazakhstan and Tunisia in 2004, the report says.

Beata Javorcik, the EBRD's chief economist, said the boom would be hard to tap. "The bad news is that it's not easy to plug yourself into the AI and defence boom, because these are goods that are complex," she said, Reuters reported. "Countries that have reinvented themselves before perhaps have an edge, because they have experience in seizing new opportunities."

For operators and investors in the corridor, the estimate gives a measure of grid headroom. In nearly half the economies the bank covered, a single frontier facility would raise peak load, the report says.

Document trail

3 sources, 2 primary

  1. Transition Report 2026-27: Frontiers of competitiveness

    European Bank for Reconstruction and Development, Office of the Chief EconomistPrimary source

  2. EBRD economies seek competitive edge as AI race heats up

    European Bank for Reconstruction and DevelopmentPrimary source

  3. Developing economies risk missing out on defence and AI boom, EBRD warns

    Reuters, via TimesLIVESecondary source

Named in this piece

  • EBRD
  • Beata Javorcik
  • Türkiye
  • Kazakhstan
  • Turkcell
  • Central Asia
  • South Caucasus